Month Construction Activities
2009 Mar Site shut down for winter
2009 Feb Site shut down for winter
2009 Jan Basement Foundation Work Completed
  • Temporary staircase into basement built and enclosed
  • Walls prepped for Core Slab
  • Propane tank installed and heating hooked up for basement
  • Core Slab installed and pinned. Covered with tarps and straw
  • Temporary lighting installed in basement
  • Walls backfilled to grade level
  • Fire extinguisher installed
  • Fence erected around construction area for protection during winter
2008 Dec Basement Foundation Work In Progress
  • Concrete poured for basement walls around the main hall
  • Steel rebar for the foundation walls completed with volunteer help
  • Forms for basement walls completed
  • Excavation and forming porch area footings completed
  • Fellowship hall porch and piers formed
  • Parking lot sub grade completed
  • Driveway entrance widened
  • Lower level steel beams installed
  • Fellowship hall porch and piers poured and back filled
  • Forms and foundation walls cleaned up with volunteer help
  • Walls tarred with volunteer help
  • Lower System Platon completed
  • Weeper installed
2008 Nov Preparation for Foundation
  • Top soil stripping completed for site
  • Basement is excavated and strip footings poured
  • Steel rebar for the foundation walls is 75% complete
  • Forms for basement walls started
  • Piers for 2 steel columns are complete and ready for steel
  • Basement clear stone is completed
  • East side of parking lot is up to sub grade
2008 Oct Construction Mobilization & Site Preparation
  • Office & storage trailers moved to the site
  • Phone, internet, hydro arrangements made for office
  • Horse paddocks relocated with volunteer help
  • Fencing completed
  • Boxes for footing in preparation for concrete pouring made with volunteer help