| Month |
Construction Activities |
| 2009 Mar |
Site shut down for winter
|
| 2009 Feb |
Site shut down for winter
|
| 2009 Jan |
Basement Foundation Work Completed
- Temporary staircase into basement built and enclosed
- Walls prepped for Core Slab
- Propane tank installed and heating hooked up for basement
- Core Slab installed and pinned. Covered with tarps and straw
- Temporary lighting installed in basement
- Walls backfilled to grade level
- Fire extinguisher installed
- Fence erected around construction area for protection during winter
|
| 2008 Dec |
Basement Foundation Work In Progress
- Concrete poured for basement walls around the main hall
- Steel rebar for the foundation walls completed with volunteer help
- Forms for basement walls completed
- Excavation and forming porch area footings completed
- Fellowship hall porch and piers formed
- Parking lot sub grade completed
- Driveway entrance widened
- Lower level steel beams installed
- Fellowship hall porch and piers poured and back filled
- Forms and foundation walls cleaned up with volunteer help
- Walls tarred with volunteer help
- Lower System Platon completed
- Weeper installed
|
| 2008 Nov |
Preparation for Foundation
- Top soil stripping completed for site
- Basement is excavated and strip footings poured
- Steel rebar for the foundation walls is 75% complete
- Forms for basement walls started
- Piers for 2 steel columns are complete and ready for steel
- Basement clear stone is completed
- East side of parking lot is up to sub grade
|
| 2008 Oct |
Construction Mobilization & Site Preparation
- Office & storage trailers moved to the site
- Phone, internet, hydro arrangements made for office
- Horse paddocks relocated with volunteer help
- Fencing completed
- Boxes for footing in preparation for concrete pouring made with volunteer help
|